The historical line between Bussoleno - Avigliana runs on a 3 kV D.C. and is electrified with a 610 mm² catenary system (adjustable wires and cables) on horizontal steel cantilevers and with a rail head height of 5.20 metres as well as a primary power supply circuit of 66kV alongside the odd-numbered track of the section in question. The project involves the decommissioning and demolition of the primary 66kV line in operation between the towns of Bussoleno and Collegno and the construction of the new overhead line between the portals outside Bussoleno and Avigliana stations with an equivalent section of 540 mm² adjustable messenger cable and the addition of a 230 mm² back-up feeder, required for the correct running of the line according to the expected operating traffic.
The decommissioning of the 66kV line will happen after the new Borgone and Avigliana traction substations go into service.
May 2019
February 2020
Bussoleno - Avigliana, Piedmont
NET ENGINEERING S.p.A.
New electrification featuring a catenary system with 540 mm² CSA wire and 270 mm² CSA wire with 3 kV D.C. for the sections and stations with phase connections, including the addition of a 230 mm² back-up feeder, and the decommissioning of the primary 66kV line.
Final design for the Modane - Turin line
Upgrades to the historical Bussoleno - Avigliana line
47.800 km of single running plain track
22.200 km of single station plain track
556 LSU-type ET masts required by the project
6,411 m³ of concrete for the ET foundations
42.026 km of 230 mm² CSA copper cable
95.650 km of 150 mm² CSA copper-silver contact wire
95.650 km of 120 mm² CSA copper messenger cable
Activation phases to keep the railway up and running and the use of non-standard supports compared with the ET technical specifications for use of the back-up feeder.
€20,000,000
47.800 km
The total distance in kilometres of the “running” and “station” plain track undergoing new electrification.
6,411 m³
m³ in total of concrete used for the new surface and deep foundations of the ET masts.
95.650 km
In total of contact wire installed for the new electrification.