Naples - Bari Railway Line, Naples - Cancello section realignment between PK 0+000 and PK 15+585

Railway line

Type of work

Working drawings and detailed design of 3 kV D.C. electric traction systems

Naples - Bari Railway Line
Naples - Cancello Section

Country/Location

Naples - Cancello, Campania

Year

July 2020 - ongoing

Project technical details

Project description

The section in question is about 15.7 km long and mainly runs in the open air (there is only one tunnel about 3 km long). It is formed of short sections with trenches, embankments and ordinary small and medium-sized prestressed concrete viaducts with a mixed steel-concrete structure.

The new section realignment is formed of the following places and main services that form part of its Electric Traction systems:

  • Casalnuovo Stop (in a tunnel)
  • Naples Afragola Station (connection with the high-speed line)
  • Shopping Centre Stop
  • Acerra Station

Technical information

Work start date

July 2020

Work end date

Ongoing

Location/Country

Naples - Cancello, Campania

Client

Systra - Sotecni S.p.A.

Brief description

New electrification featuring a catenary system with 540 mm² CSA wire and 270 mm² CSA wire with 3 kV D.C. for the sections and stations

Type of Project

Working drawings and detailed design of 3 kV D.C. electric traction systems

km/catenary mm²

37.100 km of single running plain track
8.540 km of single station plain track

Project technical details

1,103 LSU-type ET masts required by the project
5,500 m³ of concrete for the ET foundations
82.72 km of 150 mm² CSA copper-silver contact wire
82.72 km of 120 mm² CSA copper messenger cable

Critical issues

Activation phases on existing connections, a stop in a tunnel with an electric traction safety system

Final cost

€9,104,782.24

37.100 km

km of single running plain track

The total distance in kilometres of the “running” and “station” plain track undergoing new electrification.

5,500 m³

Concrete for ET foundations

m³ in total of concrete used for the new surface and deep foundations of the ET masts.

82.72 km

150 mm² CSA copper-silver contact wire

In total of contact wire installed for the new electrification.

Client
Systra - Sotecni S.p.A.

Systra - Sotecni S.p.A.

Country
Italy

Italy