This new project system has the following features:
ꞏ Single track lines with 3 kV D.C. electric traction, connecting the stations of Civitanova Marche (km 0+000), Montecosaro (km 7+452), Morrovalle (km 12+811), Corridonia (km 21+722), Macerata (km 27+181), Urbisaglia (km 34+246) Tolentino (km 45+605), S. Severino (km 55+593), Castelraimondo (km 67+149), Matelica (km 74+246) and Albacina (km 86+587); ꞏ 3 kV D.C. power supply of the overhead lines, through the ET cabins of Civitanova Marche (km 0+000) and Albacina (km 86+587), and the Traction Substations of Montecosaro (km 7+700), Urbisaglia (km 34+145) and Castelraimondo (km 66+650);
ꞏ Maximum gradient the same as the current 36%;
ꞏ Minimum curve radius of 215 m;
ꞏ Subsequent maximum cant up to 160 mm;
ꞏ Maximum length of the track transition curves compatible with the track speeds;
ꞏ The track speeds used are between 60 km/h and 115 km/h;
ꞏ To carry out the electrification of the Civitanova Marche - Albacina section and its functions under the regional conditions described above, you need to carry out supplies and jobs organised into construction macro-phases where the ET equipment set-up can be carried out in different areas and at different times across the section in operation.
January 2020
Ongoing
Civitanova Marche, Marche
SINTAGMA S.r.l.
3kV D.C. electrification project of the Civitanova - Albacina line featuring a catenary system with 440 mm² CSA wire, 220 mm² CSA wire and a rigid catenary system in tunnels
Preliminary and final design for the Civitanova - Albacina line
95.000 km of single running plain track
20.930 km of single station plain track
2,979 LSU-type ET masts required by the project
17,874 m³ of concrete for the ET foundations
182.000 km of copper-silver contact wire
135.000 km of copper messenger cable
10 sections of single track with radius curves below standard and tunnels with a smaller inner curved surface (intrados) that only allows the use of a rigid catenary system. 11 stations with modifications to the town master plan (PRG) and activation phases to keep the railway up and running. Studying special framework and non-standard uses.
&Euro; 33,619,140.46
95.000 km
The total distance in kilometres of the “running” and “station” plain track undergoing new electrification.
17.874 m³
m³ in total of concrete used for the new surface and deep foundations of the ET masts.
182.000 km
In total of contact wire installed for the new electrification.